BID TABULATION SHEET
Bid Date: November 2, 2006

*** All bids for this project have been rejected. See below for details. ***

Project Name: Environmental Remediation - Hurricane Katrina Related Damages
Southern University - Gymnasium Building
New Orleans, Louisiana
Designer: Aims Group, Inc.
4421 Zenith Street
Metairie, LA 70001
Project No. 01-107-05B-13 Part No. M2 Site Code: 1-36-007 State ID: S00303 FP&C Project Manager: Tony Palotta


Bidder Lic. No. Addenda Bond Base Bid Alt No. 1 Alt No. 2 Alt No. 3 Attestation Awarded Remarks
Cross Environmental Service, Inc. 33725 1 93,800 0 0 0 Incorrect Bid Bond Form - Must use FPC Bid Bond Form
LASCO 20126 1 109,700 0 0 0 Cashier's Check in lieu of Bid Bond
ARC Abatement I, Ltd. 42261 1 124,837 0 0 0 Incorrect Bid Bond Form - Must use FPC Bid Bond Form
Gulf Services Contracting, Inc. 25548 1 186,696 0 0 0
Zimmer-Eschette Services, LLC 43043 1 198,000 0 0 0
Insulation Technologies 18938 1 276,500 0 0 0
Associated Contractors, LLC 36841 1 339,805 0 0 0 Used Liquid Paper Did Not Initial & Cashier's Check in lieu of Bid Bond
Gill Industries, LTD 32761 1 394,416 0 0 0
Interstate Restoration Group, Inc. 41852 1 483,028 0 0 0 Cashier's Check in lieu of Bid Bond


Signed: Aims Group, Inc.
Designer
Date: 11/2/2006
Signed: Denise Marrero
FPC Representative
Date: 11/2/2006
A.F.C.: $275,000.00
Construction Time (in days): 30
Liquidated Damages: $175.00 per day

Reason For Rejection:
due to administrative error

DISCLAIMER

The information contained on this bid tabulation is unofficial and is not in any way binding upon the State of Louisiana, its agencies or subdivisions or upon the State's employees or agents. In order to request a copy of an official bid tabulation sheet, please contact the Office of Facility Planning and Control, Division of Administration.